Kshema Power has received an order from Oyster Green Hybrid Three to build a 33 kV/220 kV transmission line and an air-insulated substation for a 350 MW wind–solar hybrid project in Madhya Pradesh. The scope of work includes supplying, erecting, testing, and commissioning a 51-kilometre transmission line. 

Furthermore, the scope also covers designing, engineering, supplying, installing, executing civil works, and commissioning the air-insulated substation. The project is expected to be commissioned in July 2026. 

Earlier in September 2025, Kshema Power secured a Rs 1.08 billion contract for the construction of a 400 kV transmission line in Andhra Pradesh.