Suzlon Group has secured an order for a 100 MW wind energy project from Gas Authority of India Limited (GAIL). According to the specifications of the order, Suzlon will install 47 of its S 120 wind turbine generators, each with a capacity of 2.1 MW. Furthermore, the company will be responsible for supplying the turbines and managing the complete project execution. This includes installation, erection, and commissioning of the project.
In addition, Suzlon will provide operations and maintenance services after the project becomes operational. The power generated from the project will be used to support the decarbonisation of GAIL’s upcoming petrochemical plant in Nandurbar, Maharashtra.
Earlier in January 2026, Suzlon Group bagged a 248.85 MW wind turbine supply order from the ArcelorMittal Group through its renewable energy entity in India. The order forms part of a 550 MW hybrid renewable project in Gujarat developed for captive consumption for ArcelorMittal Nippon Steel facilities in India.