Juniper Green Cosmic Private Limited, a subsidiary of Juniper Green Energy Limited, has commissioned 100.64 MWh of battery energy storage system (BESS) capacity at its Bikaner Phase II project site. Following the commissioning, the company’s total commissioned BESS capacity has increased from 100.64 MWh to 201.28 MWh.
With this addition, the aggregate operational capacity of Juniper Green Energy Limited and its subsidiaries has reached around 2,725 MWp of renewable capacity and 600 MWh of BESS capacity.
Earlier, in September 2026, Juniper Green Beam Eight Private Limited, a wholly owned subsidiary of Juniper Green Energy Limited, fully commissioned its 75 MW wind-solar hybrid power project under its power purchase agreement with Tata Power Company Limited.
In January 2026, Juniper Green Energy Limited secured Rs 20.39 billion in debt financing from global and national financial institutions. The funds will be used to support the development and expansion of the company’s upcoming renewable energy projects.