Quinbrook Infrastructure Partners has achieved the completion of construction and commenced commercial operations of the solar asset at the Cleve Hill solar park. The project is now exporting 100 per cent of its 373 MWdc capacity. The project is located in Kent, UK.
Furthermore, the Cleve Hill solar park was the first solar and battery storage project to be consented as a nationally significant infrastructure project. The construction of the 150 MW co-located battery energy storage system is underway. The project was granted development consent in May 2020 and commenced construction in early 2023.
Earlier in February 2025, Quinbrook Infrastructure Partners acquired a 350 MW solar PV project named Millard Pass. It is located on the Rutland-Lincolnshire border in England’s East Midlands and marks Quinbrook’s second nationally significant infrastructure project. Construction of the project is expected to commence in 2026, and operations will begin in 2028.