SunSource Energy has won the contract from SECI for developing 1.95 MW of solar power with a 2.15 MWh battery energy storage station in Lakshadweep. The project will power four islands on Lakshadweep: 300 kW at Agatti, 1,400 kW at Kavaratti, 150 kW at Bangaram and 100 kW at Thinnakara. The scope of the project includes design, engineering, supply, construction, erection, testing, and commissioning of these plants. The developer will also be required to provide 10 years of comprehensive O&M for the plants from the date of successful commissioning. The project must be commissioned within 12 months from the date of signing the LoA. The tender for the project was issued in September 2019.