Southern Power Distribution Company of Andhra Pradesh tenders 10 MW of solar projects

Southern Power Distribution Company of Andhra Pradesh Limited (APSPDCL) has tendered two projects of 5 MW each. While one project will be located in APSPDCL’s region, the other one will be located in Eastern Power Distribution Company of Andhra Pradesh Limited’s (APEPDCL) region. The projects will be developed on a BOO basis. The last date for bid submission was June 16, 2017. The successful bidders will sign letters of intent (LoIs) by July 14, 2017 and PPAs will be signed within 15 days from the date of signing of LoIs. According to the tender, the projects should be commissioned within six months from the date of signing of PPAs.