Andhra Pradesh Power Generation Corporation tenders 100 MW of Solar at Ananthapuramu-II Solar Park

The Andhra Pradesh Power Generation Corporation (APGENCO) has tendered a 100 MW solar project at the Ananthapuramu-II Solar Park in Talaricheruvu. The estimated cost is Rs 4.45 billion and the project completion timeframe is 15 months from the date of issue of the letter of intent. The project will be developed on an EPC basis. The scope of work includes design, engineering, manufacturing, testing, supply, packing and forwarding, transportation, unloading, erection, installation and commissioning. The successful bidder will also have to provide O&M services for five years. The last date for bid submission is May 26, 2017.